Today was the day that the ceiling got it's plasterboard put up. My friend Robin came round to give me a hand but instead took over the job and i ended up just the labourer. Robin has done this before and being younger, fitter makes the job simple. I would have put up my scaffolding tower and when i got the plasterboard lifted on to the top of the tower it's not to difficult but Robin had other ideas.
I must say i would have taken so much longer without the valuable help i
had. This is the end of the day lights and ceiling fan all wired in and
waiting for the fittings and fan. But i will wait till the walls and
ceiling are painted first.
To work at night i have a temporary Light setup just where the ceiling fan will go.
There is a gap of 5cm on each side of the room as the plasterboard was 2.5 metres long and the room las 2.6 metres wide. I am putting up coving all round so the 5cm gap each side will be hidden.